The National Highways Authority of India (NHAI) has stepped up its highway maintenance monitoring by bringing nearly 50,000 km of national highways under a dashcam-based surveillance system. The technology will track 40 categories of road defects, including potholes, faded road markings, damaged surfaces and faulty streetlights, through cameras installed in highway patrol vehicles.
According to a report by TOI, the system is designed to make contractors more accountable, with the authority planning to automate penalty calculations for unresolved defects over the next few months.Dashcams to identify 40 types of highway defectsThe monitoring system covers national highway stretches managed by NHAI that are currently under operation and maintenance contracts.
Patrol vehicles fitted with dashcams will record road conditions during their regular rounds, with the technology capturing defects along with their precise locations and visual evidence.Read more – Ram and Sita’s hometowns bring India and Nepal closer: New Ayodhya-Janakpur train to connect two countries, passing through key stations in UP and Bihar; check full routeThe information is uploaded to a central server and shared with the contractors responsible for maintaining the respective highway stretches.
This is expected to make it harder
This is expected to make it harder for concessionaires and maintenance agencies to avoid responsibility for poor road conditions or delay repairs.A senior NHAI official told TOI that the cameras can detect potholes as small as two inches. The authority has also been preparing contractors and its field officials for the transition to technology-based monitoring.Over 92,000 defects detected in two monthsThe scale of the exercise is already becoming evident.
Data accessed by TOI showed that the dashcam system had identified 92,088 highway defects in the first two months after its rollout.Read more – Kanchipuram Blinkit delivery man clears CA exam; recalls how he rented a bicycle, rode nearly 100 km daily and watched CA lectures between ordersFaded road markings accounted for nearly 23% of the reported defects, while potholes made up around 15%.
Although approximately 72% of the identified problems have been rectified, nearly 17% are still overdue for repairs.The figures underline the maintenance challenges facing the highway authority, particularly as complaints about damaged roads and inadequate upkeep continue to draw public attention.Contractors face strict deadlines for repairsUnder the existing maintenance rules, contractors are required to address different categories of defects within specified timeframes.
For instance, potholes must be repaired within two
For instance, potholes must be repaired within two days, while faulty lights and safety issues at work zones need to be addressed within 24 hours.Unauthorised openings along highways must be closed within seven days.At present, contractors who fail to meet these deadlines can face financial penalties calculated according to the terms of their respective contracts. However, the calculation process is set to become automated in the coming months.An NHAI official told TOI that the authority has spent the past two months sensitising contractors and officials about the new monitoring mechanism.
Once automated, the system is expected to reduce delays in identifying violations and imposing penalties.Photographic proof required before defects are marked resolvedThe new arrangement also seeks to improve transparency in the repair process. Contractors and NHAI field officers can access defect reports through the central server, where every issue is supported by location details and photographic evidence.Simply reporting a repair as completed will not be enough.
Contractors must upload pictures and other details showing that the defect has been rectified. The submitted evidence is then verified before the complaint is marked as closed.According to another NHAI official quoted by TOI, this evidence-based process leaves little room for disputes over whether a particular defect was identified or repaired.The authority believes the system will also encourage contractors to carry out timely maintenance rather than allow minor road damage to worsen and become more expensive to fix.Public may eventually get access to highway defect dataNHAI is also considering opening up the monitoring system to the public at a later stage.
If implemented, road users could view details of identified highway defects and submit their feedback.This would add a public accountability layer to the existing monitoring mechanism, allowing commuters to flag maintenance concerns and track the condition of national highway stretches.Inputs from TOI