That all was not well with the Green India Mission was clear even before its approval. After the UPA-I government announced it in 2008, the Ministry of Rural Development had objected to its financial design much before the Union Cabinet approved it in 2014. But the Environment Ministry proceeded anyway and retained largely the same arrangement when it revised the Mission in 2021.
Following the Comptroller and Auditor General’s report, on November 19, the Public Accounts Committee (PAC) upbraided the Ministry for the Mission’s virtual failure and for still not having issued the implementation guidelines for the revised form. The original 10-year vision was to expand forest and tree cover by 5 million hectares (mha), improve forest quality on another 5 mha, improve forest-related livelihoods for 3 million households, and sequester up to 60 million tonnes of carbon dioxide a year.
The outlay was ₹46,000 crore. In 2014, the Cabinet approved ₹13,000 crore for 1.4 mha each of the first two objectives by 2018, but to be supported to the tune of 81.5% by Compensatory Afforestation Fund Management and Planning Authority (CAMPA), National Afforestation Programme (NAP), and MGNREGS funds. In 2021-22, the Ministry folded the NAP into the Mission and, in mid-2025, unveiled a revised version with an allocation of ₹12,190 crore to improve forest cover on 25 mha by 2030, including 24 mha through other schemes.
The government had thus expanded the primary target
The government had thus expanded the primary target but left the Mission responsible for only 1 mha. Together with the CAMPA, NAP, and MGNREGS funds never materialising, it is no surprise that the programmes to improve forest quality and forest cover have respectively fallen short by 91.8% and 97.5% vis-à-vis the 2014 target. The Environment Ministry had assembled a large programme around re
Pro-climate work in practice ought to span government schemes to deliver action and justice, and the Ministry ought to have formalised the division of responsibilities and accounting system. The PAC’s new demand that the Ministry submit an implementation timetable is insufficient. From the Jal Shakti Abhiyan in 2019 to the Dharti Aaba Janjatiya Gram Utkarsh Abhiyan in 2024, the government has often floated new programmes banking significantly on funds from existing schemes — an untenable policy when the latter also have their own obligations.
And if the VB-G RAM G scheme was to also advance climate justice, the government should not have undermined the erstwhile demand-driven funding model and shifted more financial responsibility to the States. Climate action has to be timely, for which the Union government must dedicate adequate red